In the next three years, the development of power plants is expected to reach 20,000 megawatt only.

Petra Hapsari   20 July 2017 11:15

The government decided to delay the target of its mega project of providing 35,000 megawatt electricity throughout the country from 2020 to 2025.

In the next three years, the development of power plants is expected to reach 20,000 megawatt only.

“The goal to reach 35,000 megawatt capacity will keep on going. We understand that half of power plants will not be ready in 2019 or 2020,” Energy and Mineral Resources Minister Ignasius Jonan said. “We predict that the capacity of 20,000 MW will be reached in 2019 or 2020.”

“The program will continue in the next five years, so in 2024-2025 the additional capacity can be achieved,” Jonan said.

Jonan continued that he hopes electricity in the future will not only be sufficient for all people but also affordable.

“If we see our people from Sabang to Merauke, from Miangas Island to Rote Island, their economic capability is varied. For the people here (in Jakarta) the [electricity] capacity is enough and the price is still good. But for those with income lower than GDP and live in the border, affordability is a big issue,” Johan said.

WHAT DO YOU THINK?

Up Next: The Latest British Airways Safety Video Is So British, So Funny

Brilio questionnaire

Hi, dearest Brilio English readers!

Spare some time to fill in our survey so we can upgrade our content quality for you!

Start

TOP